Sara Montes de Oca put ten questions to Andersen on the power bottleneck facing AI, the policy changes that would speed up distributed compute, and Lektra's plans for the next two years. This transcript has been lightly edited for length and clarity.
━ Lektra and the industry
Sara Montes de Oca
At a high level, describe Lektra and its mission.
Karl Andersen
Lektra is building Grid 2.0 as a distributed energy and computing network designed to handle AI's power demand in a way the current grid can't. We pay consumers and businesses for power from the solar and battery systems they already have, and that power runs AI compute on our own distributed network. We hold the first patent for distributed data centers built this way. Our mission is to make sure AI works for people, and that starts with building the AI compute and power infrastructure where energy already is instead of waiting a decade for the grid to catch up.
Sara Montes de Oca
What is driving AI compute demand, and why can't the current cloud model keep up?
Karl Andersen
AI's appetite for power is growing faster than the grid can add capacity, and the current cloud model concentrates that demand in a handful of very large data centers that each need a major grid connection. Fixing the grid the conventional way is too slow and too expensive, and consumers are already feeling it in higher electricity bills and in brownouts, some of which have already begun and more of which grid operators are bracing for.
Sara Montes de Oca
Where is the real bottleneck today: chips, power, or grid connection?
Karl Andersen
Power and grid connection are the most pressing issues. Chips get the headlines, but they can't run without electricity, and the grid can't deliver it to new data centers on the timeline AI needs. Local opposition to new data centers is part of the story too, but it doesn't change the math. And the conversation often skips what happens if we don't solve the power problem: higher electricity bills for consumers and brownouts. Leveraging the solar and battery systems already installed at homes and businesses will shave years and trillions of dollars off traditional grid buildouts.
Sara Montes de Oca
What federal or state policy, if any, would speed up distributed compute and storage?
Karl Andersen
I work on grid resilience and security as Chief Counsel at Grid Shield Alliance, so I also see these issues outside of my work with Lektra. There are three changes that would accelerate our ability to generate distributed energy and compute. The first is a faster, standard process for connecting solar and battery systems to the grid, so owners aren't waiting on a separate review for every project. The second is a clear way for those owners to get paid when their systems supply power. The third is clear rules on data sovereignty. Companies increasingly need to know where their data is stored and processed, and that is becoming a business requirement, not just a policy debate.
━ The grid
Sara Montes de Oca
You've talked about Grid 2.0. What is it, and how does it differ from the current grid?
Karl Andersen
Grid 2.0 is what we're building to meet AI's power demand in a way the current electrical grid can't. It's a distributed energy and computing network that doesn't rely on large central plants and new transmission lines. Instead, it uses the solar and battery systems that homes and businesses already own, and it pays those owners for their power. That gives us capacity that can come online faster and at a lower cost than fixing the grid the conventional way.
Sara Montes de Oca
What are the biggest obstacles with utilities and interconnection?
Karl Andersen
Time is the biggest one. Every new connection has to be studied, and large data centers can wait years to come online. Fixing the grid the traditional way would take at least a decade and trillions of dollars. Our approach starts with systems that are already installed, which means we can be online in days instead of years.
Sara Montes de Oca
Why would a business or homeowner become an energy host, and what do they get?
Karl Andersen
An energy host is a consumer or business with solar and battery systems already in place. Once they buy a product from Lektra's EdgeScale suite and we install it, we operate it remotely and sell its computing capacity, powered by the host's energy, to AI customers. We then pay the host 80% of that revenue. That turns surplus solar into income without the host having to find customers or manage the computing.
━ Lektra's products
Sara Montes de Oca
What are the two new EdgeStart products, and who are they for?
Karl Andersen
EdgeStart is a self-contained server cabinet that building owners can buy, house in a spare room, and power with the solar and battery systems they already have. Lektra installs it, operates it remotely, sells its computing capacity to AI customers through Lektra Cloud, and pays the owner 80% of the revenue. We've just launched two models. The EdgeStart RTX has eight NVIDIA RTX PRO 6000 Blackwell GPUs, and the EdgeStart B300 has eight NVIDIA B300 GPUs and draws about twice the power. Both are built for commercial and industrial building owners, solar and storage sites, and energy developers.
Sara Montes de Oca
How do your economics compare with AWS and Google Cloud for a customer?
Karl Andersen
A quick look at AWS pricing on B200s, for example, would give you around a $17.75 per hour rental rate, which does not include storage or egress fees (they store your data and you have to pay them when you want to take it off). Lektra was offering B200s last week at $6.09 per hour. So our price is roughly a third of theirs. This is true across products. Also, we have no egress fees, so customers know how to plan their compute costs effectively.
Sara Montes de Oca
What does Lektra look like in two years?
Karl Andersen
Today, Lektra's EdgeScale data centers, which operate at 20 MW or less, are online at eight sites, including a wholly owned site running in Kearny, NJ, and another coming online shortly in McKinney, TX. Our EdgeScale product suite lets commercial and industrial building owners turn their buildings into data centers, and in two years, I expect hundreds of sites using our systems across the country. This will let energy hosts run on their own solar and batteries while AI customers use that compute power to run real workloads. The result will be AI capacity that isn't constrained by our current power grid and doesn't have to wait for a traditional solution.